Latest Updates

Timeline

 

Tree Felling

Starting Thursday, February 5, all trees four-inch caliper and larger will be felled and left in place until the site design is approved by the New York State Education Department and other required regulatory authorities. Trees may not be removed until those approvals are in place. The work follows the New York State Department of Environmental Conservation tree-felling window, which requires felling before March 31 to meet environmental protections. Regulatory approvals are expected later this fall (August/September).  

Important Dates

  • Wednesday, December 17:  RFP submission to newspapers

  • Monday, December 22: Newspaper posting

  • Friday, January 9, 2026: Mandatory bid walk (site walk)

  • Friday, January 23 – 3:00 PM: Bids due

  • Friday, January 23 – 3:00 PM: Bid opening

  • Friday, January 30: Bid award following vetting period

  • Wednesday, February 4: Tree Felling Bid awarded at BOE meeting to Peter Downes & Son Inc.

  • Monday, February 16: Tree felling to begin

*Tree felling has been completed

Tree Felling Photo

 

Construction Manager

  • Friday, February 13: Newspaper posting- Request for Proposals- Construction Management Services
  • Thursday, February 19 - 3:00 PM: Mandatory Pre-Bid Conference
  • Wednesday, March 11 - 3:00 PM: Proposals due
  • Wednesday, March 11 - 3:00 PM: Proposal opening
  • Thursday, March 12 & Friday, March 13 - Mandatory Shortlisted Interviews - Memo
  • Wednesday, March 18: Proposal award on BOE agenda
  • Wednesday, March 25: Construction Manager Proposal awarded at BOE meeting to The Palombo Group